I plan of speaking at the Board of Supervisors Citizens’ Time on July 27th. Since my input is quite detailed I have prepared a White Paper to provide background. Its title is High Speed Rail Options, Hanover County, Virginia; it can be downloaded here. It has already been sent to the members of the Board.

The White Paper makes the following recommendations.

  1. DRPT and CSX provide the public with a plan for coordinating their projects.
  2. DRPT provides a thorough analysis as to why the I-95 option was rejected.
  3. DRPT demonstrates that they have studied the on-going challenges of the California project and that they have a plan to ensure that their own project will not suffer similar difficulties.
  4. DRPT demonstrates that they have thoroughly evaluated new technologies such as hyperloop trains.

I also suggest that the Board of Supervisors set up a task force of specialists to provide objective advice and analysis.

Third Rail, 3-2-3 and Hanover

I started blogging about the High Speed Rail project last year (my first post was on Christmas Eve 2015). Since then I have published 66 posts. My principal goal has been to demonstrate the folly of putting a third rail through the Town of Ashland.

Third Rail

Trying to squeeze a third rail through the already congested Ashland corridor is unacceptable for the following reasons:

  • The plan as proposed by DRPT is in violation of code. Not only does the new track have to meet modern code, so do the existing tracks. There is insufficient space to insert a third track while meeting those requirements.
  • We already have 50 freight trains moving through town every day. Approximately 6% of the cars are carrying “Highly Hazardous Chemicals’, i.e., chemicals which, were they to be released, could explode, burn or form a toxic vapor plume. Adding a third rail and increasing freight traffic would cross a safety threshold.
  • The loss of irreplaceable historical buildings and the impact of the college campus would be immense.
  • The project would be highly disruptive to the town’s economy.

3-2-3

About five months ago the DRPT added a new option: 3-2-3. It would have three tracks to the north and south of Ashland but would retain two tracks through town. For reasons similar to those just discussed this option would also appear to be in violation of code. It is also unsafe and destructive.

Hanover County

At this point there is not much more that I can do challenge the Third Rail and 3-2-3 options. I am seeking legal help regarding the interpretation of code and regulations and I am also chatting to seasoned railroad people, including CSX management, regarding changes in railroad freight traffic.

Many organizations in Hanover County, including the Supervisors, the Town Council and the Main St. organization have expressed a desire to come up with options that address the concerns of the broader Ashland community. I have been asked to help develop those options. My response is the White Paper referenced above.

Two Projects

One of the difficulties that we have had in following the High Speed Rail project is that there are actually two projects: High Speed Rail and Increased Freight Capacity. Each has its own goals, budgets and schedules but, because they are happening at the same time and same place, they have become entangled with one another, leading to confusion. (We are all on a learning curve as to what is going on. Communications from both DRPT and CSX could have been better.)

It is vital to stress that these two projects are going to happen. Merely wishing that they will not take place is not an effective response. This means that it behooves the citizens of Hanover to understand what the goals of both DRPT and CSX are, and to help those organizations achieve their goals, while protecting our community.

Define the Customer

commuter-1

In earlier posts such as Controlling the Narrative and Selling Nothing we suggested that those who oppose the DRPT proposals would achieve greater success were they to express their opposition in terms of the project’s customer — the passenger traveling along the east coast corridor. We even created a fictional business lady who travels from Richmond to D.C. We expressed some of her thoughts and disappointments as she learns more about the realities of the DRPT project. It makes similar sense to understand the goals of CSX and DRPT.

The Passenger Project

To further complicate an already foggy situation there are actually two phases to the HSR project. Phase I — which is what we are seeing now — is basically an increase in capacity. Phase II is true High Speed Rail.

Phase I — Increased Capacity

The DRPT refers to its project as the ‘Southeast High Speed Rail Corridor’. And the term ‘High Speed Rail’ is widely used to describe what they are doing. But, as pointed out in our post HSR, use of these words is  misleading. To summarize that post’s analysis, journey times from Staples Mill Rd. to Washington Union Station will be reduced from 2 hr 20 min to 2 hr and the train’s average speed will increase from 45.1 mph to a mere 52.5 mph. For most passengers, it will still be quicker to use I-95 — particularly if point-to-point times are considered.

The reality is that the current proposal to add a third track along the eastern corridor is not about ‘high speed’passenger service; what DRPT and Amtrak want is a more reliable service — one that will attract more travelers because those travelers are more confident that they will arrive at their destination on time. The third rail will help them achieve this goal because passenger trains will be less likely to be stuck behind a slow-moving freight.

Phase II — True High Speed

Acela train Ashland High Speed Rail
Acela Train

If the current project is something of a stopgap, then the question becomes, “What is the long-term goal?” We have virtually no authoritative information on this topic but we do hear that some long-term planning is going on. Clearly Amtrak would like to have a true high speed service from Boston to Miami.

They probably have a vision of something like the current Acela service running all that way. If that is their vision then we suggest that they are making a mistake. Current high speed rail technology such as Acela is old, very old. New methods of moving people far more quickly have been developed and are surprisingly mature. Moreover, if we could jump straight to these new technologies we could not only whisk our fictional business lady from RVA to D.C. in 20 minutes — we could do this with less disruption to the people of Hanover County.

In the White Paper we make the following points:

  1. One of the new technologies — hyperloop trains — is being developed. Trains run at up to 650 mph. Hence the journey time from RVA to DC goes from 2 hr 20 min to just 20 minutes.
  2. The new trains are much lighter than old-fashioned high speed trains (no locomotive, no track, no wheels). And there is no overhead catenary. Hence the structural and civil engineering challenges associated with building a hyperloop train along the I-95 corridor are much reduced.
  3. There is already competition among the nations of Europe to become the leader in this technology. Currently Finland/Sweden and Hungary/Slovakia are out front. It would be great if the United States could become one of the challengers.

My favorite quotation in this context is from one of the Swedish managers,

Expanded to all of Sweden the hyperloop makes high speed railways look ridiculous.

Let’s adapt that quotation,

Expanded to all of the United States the hyperloop makes High Speed Rail look ridiculous.

Obviously these concepts are futuristic. But a key part of the technology — electromagnetic levitation — is already in commercial use in Japan. Those trains travel at at well over 300 mph.

Freight

Two mile train
Two mile train

The situation regarding freight is difficult to follow. CSX projects 2% per annum growth in its traffic over the next 30 years. (Freight traffic actually declined somewhat during the last 12 months.) Yet they are currently taking actions that would seem to lead to a much bigger increase along our east coast corridor. These actions include:

  • Expansion of the Virginia Avenue tunnel in D.C to two tracks. Once it is finished CSX will be able to run double-stacked container trains all the way from Chicago to the south-east. This could have a huge impact on the traffic through Hanover.
  • Trains of two miles in length are on the horizon.
  • Expansion of the east coast ports in Virginia and North Carolina which will put many more containers on the eastern corridor. This growth will be fueled in part by the recent expansion of the Panama canal.
  • Potential closure of the C&O line due to reduced coal traffic.

We have been informed that CSX does not see themselves as a leader in our current project — they are merely picking up on the benefits that the DRPT project would offer them. Others are more skeptical. This is clearly a topic that merits further communication.

Conclusions

This post summarizes some of the points made in the White Paper. Other issues — including the troubled California HSR project and the lack of information to do with the I-95 option — are not discussed here.

In summary:

  1. High Speed Rail — in some form — is coming.
  2. The current ‘High Speed Rail’ project is actually a ‘More Reliable Rail’ project.
  3. It is likely that we will see much more freight traffic along the eastern corridor in coming years — although details are frustratingly hazy.
  4. It makes sense for those opposed to the current project to understand the needs and goals of the passengers who will be traveling on the new trains, and of the freight companies using the tracks.
  5. Current ‘High Speed Rail’ technology is very old. Its time is over — the trains are too slow. The use of modern technology will dramatically reduce travel times and will lessen the impact on the communities through which it travels.

 

Advertisements

One thought on “Board of Supervisors Meeting

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s